Fechas
importantes:
-25 de abril: fecha
límite para que la JCF demuestre en Washington DC que está cumpliendo con
PROMESA (Carta de senadores Tillis y Cotton de 7 de abril)
-30 de abril: gobierno tiene que presentar el
presupuesto ante la Legislatura.
-1 de mayo: termina la suspensión de litigios concedida por la Junta. Gobierno
solicita la Congreso que se extienda hasta diciembre.
http://www.elnuevodia.com/noticias/locales/nota/inciertopedirmastiempoenelplanfiscaldelgobierno-2297091/ y en cuanto a la demanda presentada sobre los GOs y COFINA http://www.elnuevodia.com/noticias/tribunales/nota/eljuezbesosadaundurorevesalgobierno-2293393/
-May 8, 2017: Oversight
Board to approve Governor’s proposed budget or to notify Governor of violations
and provide descriptions of all necessary corrective actions;
-May 22, 2017: (a) If the Oversight Board approved the proposed budget, the Legislature
shall submit to the Oversight Board the budget it adopts; (b) If the Oversight
Board notified the Governor of violations, the Governor may submit a revised
budget to the Oversight Board on or before May
23, 2017;
-May 31, 2017: (a) If the
Legislature timely submitted its adopted budget to the Oversight Board, the
Oversight Board shall approve it or notify the Legislature of its violations
and provide descriptions of all necessary corrective actions; (b) If the
Governor timely submitted a revised budget, the Oversight Board shall approve
it or submit to the Governor and Legislature its own revised, compliant
budget.
-June 7, 2017: (a) If the Legislature timely submitted a revised, compliant budget to
the Oversight Board, the Oversight Board shall issue a compliance certification
to the Governor and Legislature. (b) If the Legislature did not submit a
timely, revised, compliant budget, and continues to fail to do so through June 30, 2017, the Oversight
Board shall submit its own compliant budget to the Governor and Legislature on July 1, 2017 and that budget, pursuant to PROMESA §
202(e)(3), shall be (i) deemed to be approved by the Governor and Legislature,
(ii) deemed to be subject to a compliance certification issued by the Oversight
Board to the Governor and Legislature, and (iii) in full force and effect
beginning the first day of the fiscal year. (c) If the Oversight Board
submitted the Governor’s or its own budget to the Legislature on or before May 31, 2017, the Legislature shall
submit to the Oversight Board the budget it adopts.
- June
14, 2017: (a) If the
Legislature timely submitted its adopted budget to the Oversight Board, the
Oversight Board shall approve it or notify the Legislature of its violations
and provide descriptions of all necessary corrective actions.
-June 21, 2017: (a) If the
Oversight Board approved the Legislature’s adopted budget, the Oversight Board
shall issue a compliance certification to the Governor and Legislature for such
budget. (b) If the Oversight Board notified the Legislature of violations and
corrective actions, the Legislature shall submit a revised budget to the
Oversight Board.
-June 30, 2017: (a) If the Legislature submits a revised, compliant budget to the
Oversight Board, the Oversight Board shall approve it and issue a compliance
certification to the Governor and Legislature. (b) If the Legislature fails to
submit a revised, compliant budget to the Oversight Board, the Oversight Board
shall submit its own compliant budget to the Governor and Legislature on July 1, 2017 and that budget, pursuant
to PROMESA § 202(e)(3), shall be (i) deemed to be approved by the Governor
and Legislature, (ii) deemed to be subject to a compliance certification issued
by the Oversight Board to the Governor and Legislature, and (iii) in full force
and effect beginning the first day of the fiscal year.
-Any time through June 30, 2017: Pursuant to PROMESA § 202(f), if the Governor, Legislature, and
Oversight Board each certify that a jointly developed budget reflects a
consensus among them, then such budget
shall serve as the budget for the Commonwealth for fiscal year 2018.